HASLETT, MI - Construction began this week on Haslett Road from Park Lane to Shaw Street. The construction will take place in three phases: phase one from park lane to Okemos Road, phase two from Okemos to Marsh Road, and phase three from Marsh to Shaw Street.
During each phase, detours will be set up and posted along the road. From Marsh Road to Shaw Street, only eastbound traffic will be allowed. A detour will be set up for westbound traffic.
The construction along Haslett Road includes storm sewer and gutter construction, as well as rehabilitating the existing asphalt and resurfacing the roadway.